Skip to Main Content

Case Study

Hargrove Engineers + Constructors Use Ansys Cloud to Extend the Life of a Client’s Critical Asset


“This type of nonlinear analysis is very computationally intensive, so we leveraged our Ansys Cloud solving capabilities to give us a boost we needed in terms of extra cores.”

-Benjamin Turner, Senior Fixed Equipment Engineer/Hargrove Engineers + Constructors

 


Calculating the critical buckling pressure of a heat exchanger takes time. And when a heat exchanger is already deformed and corroded inside a chemical plant, every second counts. Hargrove constructs some of the most complex industrial plants, ensuring the safety of all involved. When time was of the essence, Hargrove was able to access more processing power, FAST with Ansys Cloud.


Challenges

Hargrove Engineers + Constructors was tasked with performing a Fitness-for-Service (FFS) analysis on a client’s process condenser. The condenser, a heat exchanger comprising four different materials and thousands of tubes, experienced corrosion and/or erosion opposite its inlet nozzle. Field ultrasound inspections revealed a thickness below the API- 579/ASME Code minimum allowable thickness for external pressure.

 

Engineering Solution

FFS-1 general metal loss level 3 FFS analysis confirmed the existing thickness was inadequate and required corrective action. Elastic plastic materials and large deformation theory was used to assess the maximum external pressure before buckling occurs. Following the FFS analysis powered by Ansys Mechanical Enterprise, engineers at Hargrove recommended a novel addition of stiffener rings without cutting the main pressure membrane. As a result, the designed stiffener rings mitigated the buckling risk by elevating the Maximum Allowable External Pressure (MAEP) above Code minimums.

 

Benefits

  • Leveraging Ansys Cloud’s high-performance computing capabilities, Hargrove quickly scaled up their processing power to run simulations faster than ever, significantly reducing the development time and overhead costs. 
  •  The vessel required modification and four stiffening rings were added.
  • The product of this analysis provided additional life for the client’s asset, mitigated costs associated with significant repairs and/or total replacement and prevented lost production.

Ansysができること

お問い合わせ

* = 必須項目

お問い合わせいただき、ありがとうございます。

当社はお客様の質問にお答えし、お客様とお話できることを楽しみにしています。Ansysの営業担当が折り返しご連絡いたします。

フッター画像